Measurement and Quantity Tracking Software

A quantity recorded by the contractor is the contractor's measurement record. A jointly recorded and acknowledged measurement provides stronger evidence of agreement, subject to the contract and the records required under it. A great deal of billing dispute lives in the distance between those two things.

Construction measurement software holds how quantity gets established and agreed on a project. It carries the measurement sheets recorded at site, the joint measurement done with the client's engineer or PMC, the measurement book entries that form part of the contractual record where required, the standard of measurement each item is measured under, executed quantity item by item against the quantity that was awarded, and the photographic evidence behind entries for work that will shortly be concealed. With Pentoggle, a contractor can describe its measurement formats, sites and contract requirements and generate the starting application around them.

Measurement is upstream of billing and the two are often treated as one job. They answer different questions. Measurement establishes what quantity was executed and supports getting that quantity agreed. RA billing takes agreed quantities and turns them into money through the abstract, deductions, advance recovery and retention. A contractor with disciplined billing and weak measurement will still lose value, because the billing engineer can only bill what the measurement can support.

Most construction companies already run Tally or a comparable system for accounting, which can handle job costing and project financials, and drawings sit in AutoCAD, Revit or similar tools. What sits outside both is the record of what was measured at Tower B on Tuesday and what was acknowledged against it.

Key takeaways

  • Measurement recorded alone is the contractor's own record. Measurement recorded jointly and acknowledged provides stronger evidence of agreement, subject to the contract and the records it requires.
  • Some measurement windows close physically. Once concrete is poured or a trench is backfilled, what was underneath cannot be measured again.
  • Two competent engineers measuring the same wall can get different quantities, because the method of measurement decides what gets deducted.
  • Executed quantity has to be visible against awarded quantity while work is in progress, otherwise quantity overruns are discovered when the bill is cut.
  • A useful weekly number is executed quantity as a percentage of awarded quantity, item by item, sorted from the top.

What the measurement book does well, and where it stops

The measurement book is a serious instrument and it deserves respect before anything is proposed to replace it. In formal public works procedures such as CPWD's, measurement books are controlled records with requirements around numbering, corrections, signatures and certificates, and traceability. Other contracts and departments can use different procedures, including computerised measurement records, so the governing contract and department requirements should control. In a dispute or arbitration years later, a properly maintained MB can be important evidence of the quantities recorded and agreed. An Excel file containing a quantity does not, by itself, demonstrate that the other party agreed to that quantity.

Any measurement application has to preserve what makes the contractual measurement record reliable: sequence, attribution, an auditable change history, and the acknowledgements or signatures required under the applicable contract. An application that allows a quantity to be changed without an audit trail can be weaker than the formal measurement record it is intended to support.

Where the paper system stops is not about the paper.

It exists in one place

The MB is at site. The billing engineer is at the office. The quantity has to travel by transcription, which means it gets copied from a field sheet into the MB, from the MB into a measurement sheet, and from there into the abstract. Three copies, three opportunities to diverge, and a divergence that only surfaces when the client's total and yours differ.

It cannot be queried

Which items have crossed eighty percent of their awarded quantity is a question the MB physically contains the answer to and cannot be asked. Somebody has to add up entries across pages, which takes a day, which means it gets done before a bill and not before the work.

The evidence sits somewhere else

Photographs of reinforcement before a pour are in somebody's phone and in a WhatsApp group. They are not attached to the measurement entry they support, so when the entry is questioned eight months later the photograph cannot be found.

It has no view across projects

A company running six sites has six measurement books and no way to see all six.

What measurement software holds

Measurement sheets in working format

Item, location, and the number, length, breadth and depth entries that produce the quantity, so the calculation is visible rather than only the result.

Joint measurement records

Who measured, when, which representatives of the client or PMC participated, and the acknowledgement or signatures required under the applicable contract, held against the specific entries they cover.

The standard each item is measured under

Which method of measurement applies and what it deducts, recorded against the item, so the rule is agreed at award rather than argued at billing.

Executed against awarded quantity

Item by item, quantity executed up to date against the quantity in the contract BOQ, with the deviation visible as work proceeds.

Evidence attached to the entry

Photographs, level readings, bar bending schedules or test references held against the measurement they support, particularly for anything about to be concealed.

Part rate and stage entries

Work measured partially complete at an agreed part rate, with the stage recorded, so partially executed items can be billed without being closed.

Location and structure breakdown

Quantity by block, tower, floor, chainage or elevation, depending on what the project is, so measurement matches how the site is actually organised.

Extra items and non-BOQ work

Work executed that has no item in the awarded BOQ, flagged at measurement so it goes to rate analysis and variation approval rather than into a bill that will be cut.

Concealed work has a measurement window, and it closes

This is the part of measurement that has no equivalent in most other workflows. Some quantities can be verified at any time. A finished floor area can be measured next year. Most of the value in a structure cannot.

Reinforcement is measurable until the concrete is poured. Excavation is measurable until it is backfilled. Conduits and piping in a slab are measurable until the slab is cast. Waterproofing is measurable until the screed goes over it. Once the work is concealed, direct verification can become difficult or impossible, so the contemporaneous measurement record and its supporting evidence become much more important.

This changes what measurement software is for. For visible work it is a convenience, and a good one. For concealed work it is the difference between a quantity that gets certified and a quantity that gets disputed by a client engineer who joined the project after the pour and has no reason to accept somebody else's number.

The practical requirement is that the record has to be made at site, before the concealment, with evidence attached, and where practicable with the participating representatives identified and the required acknowledgement or signatures captured according to the contract. That is a phone in somebody's hand standing next to the reinforcement, not a form filled in at the office three days later. It is also the single strongest reason for site teams to adopt a measurement application, because a site engineer who has once lost an argument about buried quantity does not need to be persuaded twice.

Two engineers, one wall, different numbers

Measurement disputes are usually assumed to involve somebody being dishonest. Most of them do not.

The method of measurement decides what is counted and what is deducted, and the rules are specific. Whether an opening below a certain area is deducted from brickwork. Whether plaster is measured on both faces and how jambs and soffits are treated. Whether excavation is measured to authorised dimensions or to what was actually dug, which matters enormously when the sides have sloped. How steel is computed and whether laps, chairs and wastage are included.

Two engineers applying different rules to the same wall will produce different quantities and both will be able to defend their figure. The disagreement is real and it is not resolvable by measuring again, because the measurement was never the problem.

Where possible, record the applicable measurement standard and basis against each item at the start of the contract, and apply it consistently unless the contract or an approved change requires otherwise. In a paper system this lives in somebody's head and leaves when they leave. In an application it sits on the item, which means a new billing engineer or a new client representative inherits the agreed basis rather than reopening it. This is unglamorous and it removes much of this category of dispute.

Measurement is where quantity overruns should be caught

An item executes beyond the quantity it was awarded. Site had a reason, usually that the actual condition required it. Nobody raised a variation, because raising variations is a commercial job and the person watching the quantity grow was an engineer.

The overrun is then discovered at the bill, when the client's engineer disallows the excess for want of an approved variation. By then the work is built, the negotiating position is gone, and the conversation the RA billing guide describes has already been lost.

Measurement is the correct place to catch this, because measurement is the workflow that establishes executed quantity while the work is still happening. An item at eighty five percent of its awarded quantity with two floors still to go is a variation to be raised this week. The same item at a hundred and twenty percent after the pour is much harder to resolve and may become a claim rather than an approved variation.

Many contracts permit some deviation from the awarded quantity at the same rate and require a revised rate beyond that, so the threshold that matters is contractual rather than universal. Whatever your contract says, the requirement is the same: the deviation has to be visible before it is crossed. See change orders and variations for the approval side.

Where measurement looks different by business type

  • Infrastructure and Road Contractor Software, where measurement runs on chainage, level books and cross sections, and earthwork quantity comes from computed sections rather than direct measurement.
  • MEP Contractor Software, where measurement is counts of points and fixtures and running metres of cable, conduit and ducting, much of it concealed in slabs and shafts.
  • Facade Contractor Software, where measurement is elevation-wise and panel-wise and has to reconcile against what was fabricated.
  • Interior Fit-Out Contractor Software, where measurement is area and running metre based and is checked against approved samples as much as against dimensions.
  • Waterproofing Contractor Software, where the measured area is also the area under warranty, so the record has to survive for years.
  • Labour Contractor Software, where measured output per unit is what wages are computed against.
  • PMC Software, where the firm measures and certifies on the client's behalf and needs the same record from the other side.

Why construction companies choose Pentoggle for measurement

Recorded at site, on a phone

Measurement entered where the work is, by people standing next to it, with photographs attached to the entry.

Your measurement format

Number, length, breadth and depth, chainage, level books, point counts or elevation-wise, described to match what your contracts and your sites actually use.

Deviation visible while work is live

Executed against awarded quantity item by item, so overruns become variation requests instead of disallowed lines.

Joint measurement held as evidence

The participating representatives, date, required acknowledgement or signatures, and supporting photographs, kept against the entry rather than in a WhatsApp group.

Works alongside Tally and your ERP

Measurement feeds billing. Accounting stays where your CA already works.

A useful number for measurement

Executed quantity as a percentage of awarded quantity, item by item, sorted from the highest.

Physical progress tells you how the project is doing. This number tells you where the project is about to stop being billable. Items at the top of that list are the ones where a variation needs raising while the client still has a reason to consider it.

Look at it weekly, and look at the items nearest their awarded quantity rather than the whole BOQ, because on most contracts only a small number of items will ever cross their ceiling and those items are often identifiable early in the project.

The caveat matters as much as the number. It is only as current as the measurement behind it. If measurement is running well behind execution, an item showing eighty percent may already be past its ceiling on the ground, and the figure will look reassuring while the problem has already happened. A measurement lag makes this number worse than useless, because it is confidently wrong.

Ready to build measurement software?

In practice, the quantity you can evidence is the quantity you can rely on.

Related resources

Frequently asked questions

Construction measurement software records what quantity of work has been executed and supports the process of getting it agreed with the relevant parties. It holds measurement sheets, joint measurement records with the acknowledgements or signatures required under the applicable contract, measurement book entries where applicable, executed quantity against awarded BOQ quantity, and the evidence supporting each entry.